The Energy Regulatory Agency under the Ministry of Energy received 1174 applications during the first half of the year for connection to electricity network through the Technical Councils operating at “ASAN Service” and “ASAN Utility Centers”.

227 applications in January, 261 in February, 148 in March, 179 in April, 200 in May, 159 in June were received.

The implementation of 1148 applications within the first half of the year was ensured, and 26 applications were not implemented due to incompatibility in the submitted documents.

On the basis of applications received by the Technical Councils in this period, entrepreneurs ordered 19122,5 kW of energy and 3399680,01 AZN were paid as connection fee.

During this period, all applications were received at ASAN Utility Centers No. 1 and No. 2 and through Technical Councils established at ASAN Service Centers in Sumgait and Ganja cities.