The Armenian armed forces, which continues to violate the norms and principles of international humanitarian law, have also fired on the energy infrastructure in Goranboy, Tartar, Agdam, Fuzuli and Agjabadi.

10 kV Telestudio overhead line from 35/10 kV Khangarvand substation in Goranboy, and 10 kV Azizbeyov, 2nd Subartesian overhead lines from 110/30/10 kV Naftalan substation were repeatedly shot in Goranboy. The 0.4 kV distribution network in Tapgaragoyunlu is useless, repair and restoration work has not yet been possible.

10 kV AzGes №3, Sarijali №11 overhead lines from 110/35/10 kV Tartar substation and 10kV Borsunlu №3 from 35/10 kV Demirchiler substation were shot and restored in Tartar.

35 kV Horadiz-Boyuk Bahmanli overhead line, as well as 10 kV Shukurbayli, Gazakhlar, Babi and Alkhanli overhead lines from the 35/10 kV Horadiz and Mahmudlu substation was shot in different places and then restored in Fuzuli.  In Alkhanli and Shukurbayli villages, the 0.4 kV distribution network is useless, repair and restoration work is under way.

110 kV Tazakand-1, Tazakand-2, Khindiristan-1 and Khindiristan-2 overhead lines were shot in Agdam.  These lines have also been restored.

In Agjabadi, 10 kV Minakhorlu from 110/35/10 kV Karabakh substation and 10 kV PMK-4 overhead line from 35/10 kV Qiyamadinli substation were shot down and restored.

According to the latest data on gas supply, the gas supply of Tapgaragoyunlu village of Goranboy remains to be limited. At present, natural gas has been supplied at more than 50% of Fuzuli region. The gas supply of 53 residental settlements, except Tartar city and 51 villages, 25 villages of Agjabadi, a village and 5 settlements of Agdam, has been suspended.