Connecting to ETC
Application for connection of construction facilities to the electricity network
Consumers belonging to the household group can apply for the supply of electricity (capacity) to existing or future construction facilities through "ASAN service", "ASAN Utility", Small and Medium Business houses (SME houses) or e-government portal.
List of required documents
- ID cards;
- Document confirming ownership (Registration card, extract on state registration of property rights (together with technical passport or plan-scheme);
- Document on required power capacity and quality indicators (cargo report)
- Customer's mobile phone number, postal and e-mail address (if e-mail address is available)
Detailed information on the connection of construction sites to the electricity network can be found at this link.
Service fee and connection period
It is determined by the resolution of the Cabinet of Ministers of the Republic of Azerbaijan No. 399, dated 3 November 2023 and the Resolution of the Tariff Council of the Republic of Azerbaijan No. 4, dated 3 May 2024.
Installation of electricity meter
Provision of household consumers with electricity meters is supplied, installed and replaced at the expense of the energy supply company.
Given that general technical conditions are provided for connection of residential buildings to the power supply network and the requirements of these technical conditions are met, separate technical conditions, project documents and connection fee are not required for connection of apartments located in these buildings to the power supply network.